1) Superstructure Description
Uniform Building Code Construction Classification Type Two One Hour Rated
Ground Floor concrete slab-on-grade Capacity: 250 psf Floor Live Load
2nd Floor 20 gauge metal deck & concrete fill over steel framing Capacity: 80 psf Floor Live Load/20 psf Partition Load
3rd Floor 20 gauge metal deck & concrete fill over steel framing Capacity: 80 psf Floor Live Load/20 psf Partition Load
4th Floor 20 gauge metal deck & concrete fill over steel framing Capacity: 40 psf Residential Floor Live Load
Primary Frame: Structural steel beams & columns
Roofing Systems: 80 mil. single ply membrane over rigid insulation over 20 Gage metal deck & concrete fill over steel framing. Perimeter tile mansard over fire resistant plywood over light gage metal framing.
2) Exterior Architecture
Overall building height: 59 – 11 to top of roof coping at Stair Number Two.
Floor to floor height: 12 – 8 between First and Second Floors
12 – 8 between Second and Third Floors
12 – 8 between Third and Fourth Floors
Exterior wall construction: Two-Coat Plaster over exterior gypsum sheathing over metal stud framing with tile detailing
Exterior window system: Pre-finished aluminum storefront, with one- inch high performance insulated glazing
3) Site Features
Uncovered on-site parking available: 13 Spaces
Site features: Parking Lot landscaping exceeding minimum City of Chico requirements. Decorative concrete hardscape with planters & street trees on both Sixth & Main Street frontages
4) Building Systems
Heating and Air Conditioning System: Variable Air Volume system with rooftop air handlers & building heat boiler
Total cooling capacity: One Ton capacity per 250 gross square feet of building area
Electrical System: 1200 Amp, three phase four-wire system. Residences metered separately from commercial lease spaces
Communications systems: Intercom at Lobby doors
Fire suppression systems: Fully Sprinkled
Security Systems: Video Surveillance
Building access: Main Street and Sixth Street Lobby Doors and exterior door at Stair No. Two controlled by proximity card readers
5) Interior Common Area Features
Elevator: 2,500 lb capacity hydraulic elevator
Restrooms: Mens and Womens accessible restrooms, Second, and Third Floors for exclusive use of building occupants.
Lobby Finishes: Stone or stained concrete floors with stone or painted wood base & trim. Textured and painted ceilings and soffits with perimeter cove lighting, recessed down-lighting and decorative sconces.
Public Corridor widths: 5-0 Minimum

 